PM Submission - John Cochrane - MCU21/0110
“Adamson Town Planning, specialising in providing higher order town planning advice”
Under the relevant overall outcomes for the Earthworks code:
a) the earthworks will be designed and constructed to be structurally sound (OO(a));
b) all onsite works will provide for land stability with further geotechnical advice is to be
obtained and submitted with a development application for operational works (OO(b));
c) the subject site does not contain contaminated land (OO(c));
d) there are no flooding and drainage issues on the subject land, and the stormwater
management for the proposed development has been addressed with stormwater to be
managed using the existing internal lake system in the golf course (Lot 3 on
SP178340)(OO(d));
e) the proposed earthworks will not adversely impact upon groundwater, watercourses, or
wetlands (OO(e));
f) the loss of some native remnant or regrowth vegetation is unavoidable. The development
will have some impact upon NJKHT’s for which an environmental offset is to be provided.
Having regard to the advice provided by Gondwana Ecology (refer TEA – Appendix B)
the proposed development will not have a significant impact upon ecological values given
to the existing level of disturbance and the site and vegetation being isolated and
segregated from the surrounding Noosa National Park (OO(f)).
The proposed development will require earthworks across a relatively large portion of the site,
much of which has been previously disturbed. The proposed development will not unreasonably
impact on the natural environment having regard to the TEA (discussed above). The proposed
earthworks will not adversely impact upon other properties and will provide a safe and secure
work environment.
The proposed development is consistent with the Earthworks Code or could be conditioned to
comply with the assessment benchmarks. The extent of earthworks to be undertaken on site will
be addressed with a further development application for operational works.
Water Quality and Drainage Code
With respect to stormwater management and maintaining water quality, the existing stormwater
drainage infrastructure within the adjoining golf course site (Lot 3 on SP178340) is privately owned
and maintained by the applicant. The existing Noosa Springs Golf and Spa Resort facilities utilise
the existing onsite stormwater drainage system, as an integrated development. It should be noted
that under covenant, the facilities and infrastructure on the subject land and the golf course are
treated as an integrated development, and these allotments are unable to be sold separately.
The Engineering Report (Appendix D) advises the existing infrastructure has the capacity to
convey the stormwater from the proposed development. Upgrades to the internal drainage
network will be undertaken as required. The increase in flows from the development will not cause
adverse impacts or actionable nuisance to surrounding properties.
Significant capture of stormwater runoff is achieved in existing constructed waterbodies within
the golf course. Harvested rainwater is utilised for irrigation of the Noosa Springs Golf Course.
The Engineering Report advises the existing constructed waterbodies provide frequent flow
Noosa Springs Boutique Hotel – GH Australia Pty Ltd Page 54
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (PM Submission - John Cochrane - MCU21_0110.msg)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.