Log in to see the plans as drawn4.4 Road infrastructure Operations & Maintenance Plan
Operational and maintenance activities are fundamental for the ongoing management of the road
infrastructure; it is considered an investment rather than a liability. The road infrastructure assets
rely on operational and maintenance costs for the serviceability of the assets identified in this plan.
These activities are a significant annual investment that directly influence the potential for road
infrastructure assets to reach its intended service life. The ongoing development of asset knowledge
through asset inspections, improved maintenance activities, subsequent defect monitoring and
repairs are fundamental in developing sustainable intervention levels for renewals and replacement
of road infrastructure assets.
Budget Forecast Forecast Forecast Forecast Forecast
Year 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
O&M $12,386,149 $12,753,443 $12,552,794 $12,924,469 $13,031,769 $12,964,520
Forecast Forecast Forecast Forecast Forecast
Year 2024/25 2025/26 2026/27 2027/28 2028/29
O&M $13,055,339 $13,196,437 $13,441,892 $13,405,436 $13,770,707
Table 2: Annual Operational & Maintenance Costs by Asset Group
Maintenance and operational costs are identified to ensure council understands the whole of life
costs associated with the day-to-day management of road infrastructure assets. The figure below
identifies the long term financial commitment required in maintaining assets. In order to maintain
assets to an acceptable level, the cumulative costs over a ten-year period will equate to $130m. It is
proposed to develop a more detailed list of operational and maintenance activities per annum by
asset class and utilise the T1 asset management system to identify maintenance by the breakdown
of asset classes within the road infrastructure asset classes. In addition, more detailed and longer
term planning for maintenance has been identified as an improvement from this AMP.
10 Year Operational and Maintenance Costs
2029
2028
2027
2026
2025
2024
2023
2022
2021
2020
2019
$0 $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000 $14,000,000 $16,000,000
Sealed ( with Signs & Lines) Gravel Rd (with signs & lines) Road Furniture Landscaping / Mowing Car parks
Figure 6: Road infrastructure Operating & Maintenance Costs & Forecast
Asset Management Plan: Roads Infrastructure Page 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.