70. A Waste Management Plan (Operational) in accordance with Planning Scheme Policy
No.9 "Waste Management Multi-Dwellings and Commercial and Industrial Premises",
shall be developed and implemented on site, the contents of which shall be endorsed
by Council's Environment & Landscape Assessment Unit prior to or at the time an
application is made for operational works. The Waste Management Plan must include
the following as a minimum: -
70.1. The types and estimated volumes of waste that will be generated from the
activities approved within the development.
70.2. Methods to be used for dealing with garden waste.
70.3. Initiatives to minimize waste either by waste prevention, reduction, re-use or
recycling.
70.4. Description of procedures and clearly identified site responsibilities for all site
occupants for getting all waste to the bins; the storage of bins and the
collection of bins by the contractor.
70.5. A description of the design details of waste storage and recycling areas
including size, location, elevation and floor plan, methods of bin washing and
system to prevent storm water getting into sewer via the bin wash.
70.6. A description of types and volume of waste storage containers to be used,
and the collection frequency of containers,
70.7. The waste and recycling storage area shall include the provision of
containers for all waste and recycling materials including putrescible matter,
non-recycling waste, paper/ cardboard, glass, aluminium/steel cans, waste
oil, styrofoam boxes, etc, and bin washing facilities connected to sewer.
UNITYWATER
Water & Sewage
71. A single Unitywater installed primary water meter must be provided immediately inside
the property boundary of each Lot (excluding balance Lot 1). Additional water meters
must be installed for each tiUe of a community tiUe or sub-lease scheme. Meters must
be Unitywater approved, installed in accordance with Unitywater requirements and
remain accessible at all times for reading and maintenance purposes.
72. The fire-fighting demand on Unitywater's water supply system from the development
must not exceed 15litres per second.
73. Construction activities must not impede the access of Unitywater or Fire Brigade
personnel to vital infrastructure (eg. valves, fire hydrants and sewer access chambers)
74. A minimum clearance of 1.5 metres must be maintained between Unitywater sewers
and proposed building envelopes, buildings (including roof overhang) and other
structures.
75. The proposed bio-retention basins must be located a minimum of 1.5 metres from
Unitywater sewerage infrastructure and clear of any sewer easement.
76. The level of the existing sewer access chambers within the development site must be
adjusted to suit the proposed finished surface levels. Work must be undertaken by
Unitywater at the applicants cost.
PD-OA-FM58/5-02l0412009 Page 13 of 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix A - Copy of Existing Approval.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.