GENERAL COMMITTEE MEETING AGENDA 18 APRIL 2017
Page 53 of 59
GENERAL COMMITTEE MEETING AGENDA 18 APRIL 2017
A SUSTAINABLE COUNCIL
No. Project Responsibility eS Terry
1 Development of sustainability measures aligned with Council's Executive Manager The development of sustainability measures will progress in the consideration Behind Schedule @
adopted Sustainability Principles of major strategies and plans currently under development. Draft indicators
have been prepared and will be further reviewed by the internal Working
Group. Given the newly adopted organisational structure, consideration will
also be given to the membership of the group going forward.
2 Implementation of Emission Reduction Policy Executive Manager With the adoption of the Zero Emissions Noosa Organisational Strategy, work On track @
has commenced developing a detailed Action Plan and to address resourcing
requirements. The recruitment process for a temporary project resource to
assist with the implementation of actions was commenced in March 2017.
3. Implementation of ICT Roadmap Director Corporate Services Cloud transition to occur May 2017. Eplan project has commenced (authoring On track @
of new Noosa Plan). Internal Technology One mapping system completed with
training sessions scheduled. Cl anywhere Procurement to be implemented in
the June quarter.
4 Implementation of Workplace Health & Safety Action Plan Human Resources Manager The two year Workplace Health & Safety Plan has been broken down into On track @
detailed Monthly Action Plans. All responsible staff have been trained in their
responsibilities and actions are all being completed under the supervision of
the Leadership Team. The Monthly Action Plan and associated Rectifications
(RAPs) are visible on the intranet and discussed at each Leadership Team
meeting. 100% of actions have been completed and verified. Workplace
Health & Safety policies are in place.
5 Implementation of Asset Management Roadmap Asset Planning Coordinator Roadmap activities are well underway after delays with recruitment. Current Behind Schedule @
schedule is being reviewed for 2017/18.
Page 53 of 59See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.