QUESTION 1
What is the timeline for remediation works to restore and rehabilitate the Noosa Daintree Estate, including but not contained to:- removal of obnoxious weed, tree pruning, fallen debris, mowing and slashing of causeway. In addition, an ongoing maintenance and management plan for the estate land and assets.

Response provided by Director of Infrastructure, Shaun Walsh
In the next 2 months we have scheduled the following works in preparation for the traditional storm season:
  • cleaning out the culvert on Golf links drive and the adjacent in the National Park – under the conditions of the permit issued by National Parks and Wildlife Service
  • Tree pruning at various locations
  • Scheduled mowing 
We are also scoping the following additional initiatives:
  • Engineered rehabilitation of the open drain to encourage water flow and reduced ponding of water in areas – this will take time to survey and design and come up with an effective solution 
  • Additional street signage to support children safety in Homestead Dr.
Council staff have commenced preparation of site-specific maintenance Plan for Daintree Estate to respond to its specific drainage characteristics, inclusive of a more proactive inspection regime in order to schedule any reactive maintenance.  The preparation of an exclusive and site-specific maintenance plan is an initiative in response to Councils desire to maximise the drain performance to the maximum extent possible during rain events.

QUESTION 2
Has or did Noosa Council apply to the relevant department to revoke the permits required for ongoing maintenance from Noosa Daintree Estate through to McKinnon Drive.

Response provided by Director of Infrastructure, Shaun Walsh
Council currently operates under a short-term permit from Queensland National Parks and Wildlife Service to undertake maintenance works in the open drain area adjacent to Golf Course Drive but within the adjacent Harry Spring Conservation. 
Council has submitted an enduring revocation request to Queenland National Parks and Wildlife Service to extract a potion of Harry Springs Conservation Park to allow drain maintenance works in this location to more efficiently delivery future works. This revocation only applies to the existing cleared area adjacent to Golf Course Drive and as envisaged by the original stormwater system design.  To be clear it does not extend to include the natural creek corridor through the Conservation Park through to McKinnon Drive. It is important to note that the Daintree Estate’s stormwater channel is designed to hold stormwater during rain events, and inundation of the parkland and roadway and is a normal and expected function of this system.    The topography downstream of the site is very gentle and low lying and the slow drainage characteristics perform as expected as part of the natural Wooroi Creek and adjacent Noosa River system.




This summary follows this item’s minutes. The established voting totals use their existing method while differences are checked against the full records.

What was said?

Named discussion on NoosaWatch TV

These actual transcript passages match the item’s wording. The start and end of the item’s discussion are not yet confirmed; these excerpts are not measured item airtime or exact decision moments.

Helen Nugent23:48
Thank you for hearing me today. Just as associated background material, I'd like bring to your attention, on the 18th of December 2024, we received an email from Alex Neville to the resident of 15 Homestead Dr, thanking the rate payer and the resident for his time, and committing to below, in reference to identity number RM2024 two four dash two four nine six he stated, "I've pruned trees around the road and drainage channel, cutting back the trees blocking street lights, and updating the new year on the progress of our permit application to national parks department, maintenance to the drainage channel. Treaties of tidying up that homestead roundabout and adjacent fences. Management of all the singapore Daisy. Pressure washable bridge and repair of select tiles. On the 28th of March 2025, we received an email from Sebastian koplick, this time with a new reference number. RM2025/06740.XUY. Committing to the repair of the bridge and a fortnightly mulching schedule, and improved ways to manage the watercourse. My question is, what is the timeline for the remediation works to restore and rehabilitate the Noosa Daintree Estate, including, but not contained to, removal of obnoxious weeds, tree pruning, fallen debris, mowing and slashing of the causeway, in addition to ongoing maintenance and management for the estate land and assets.
Helen Nugent26:43
Yes, my second question may have been part of the answer be, but the enema we're an email was received from the Noosa electoral office on 9 April 2025. The Noosa electoral office advised they have continued conversations with the minister for the environment, including the need for a long-term solution. You are aware, activities in a protected area fall under specific legislation. In this instance, the nature conservation act 1992, nature conservation and protected areas management regulation 2024, and the aboriginal cultural heritage act 2003, require careful consideration when permitting works in a protected area. Noosa Shire Council requested and received a permit and provided the associated appropriate documentation to: 1. Remove palm fronds by hand up to five metres beyond the existing cleared 2. Maintain that area to ground level as per approved plans from 2014. The intent is to improve water flow and reduce flooding risk. It does not permit broader debris clearance. Through to McKinnon Drive as works are restricted to this five metre zone under the nature conservation act. The electoral office further stated they encourage Council to revoke the area from protected area to Council ownership. Allowing them to progress works on the area without permits and will work with Council to progress the revocation request once submitted. The current permit is 12 months, allowing work this season and next, just remind 2014, revocation once submitted. The current permit for 12 months, this will in effect provide a two-year period for the Council to apply for a revocation and a further email we've received a question from Alex Neville dated the 18th of December 2024, an update in the new year on the progress of our permit application to the national parks department. Ms Nugent, would you be able to move to the question please?
1 suggested discussion start time
  • 1436.0 seconds on the council source timeline · Recording time not yet verified. The end of the discussion is not yet confirmed.

The supporting record

Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.