CN25114 - Contract For Project Management Services - 2025 Disaster Reconstruction Funding Arrangement

← Meeting agenda & transcript

See the votes on this matter →

What was decided?

The minuted decision sequence

No separately labelled carried Council Resolution has been identified here. Read each formal event and the complete item minutes; a lost motion is not necessarily the final outcome.

1Committee RecommendationCarried

Moved: Nicola Wilson · Seconded: Karen Finzel

That Council

A. Note the report by the Disaster Reconstruction Coordinator to the General Committee Meeting dated 14 July 2025 and;

B. Award Contract No.CN25114 for Reconstruction Project Management Services under a schedule of rates contract to Northlane Pty Ltd t/as Northlane Consulting Engineers;

C. Delegates to the Chief Executive Officer the power to negotiate, finalise, execute, and do all the things necessary to administer the contract on behalf of Council;

D. Delegates to the Chief Executive Officer the power to amend the contract up to 11.5% of the total contract value;

E. Approve the budget allocation for the supporting services and costs associated with the delivery of this program. This includes:

i. $200,000 for cost recoverable project support. This is recovered monthly via the directed Disaster Reconstruction Funding Arrangement finance program.

ii.$486,751 for non-recoverable costs but essential to the receipt of grant funds and delivery of reconstructed assets.

Carried.

For 3 named

Karen FinzelJessica PhillipsNicola Wilson

Against 0 named

No names recorded on this side.

Official minutes · section 1

Read complete item-specific minutes
Committee Recommendation
Moved:Cr Nicola Wilson
Seconded:Cr Karen Finzel
That Council
A. Note the report by the Disaster Reconstruction Coordinator to the General Committee Meeting dated 14 July 2025 and;
B. Award Contract No.CN25114 for Reconstruction Project Management Services under a schedule of rates contract to Northlane Pty Ltd t/as Northlane Consulting Engineers;
C. Delegates to the Chief Executive Officer the power to negotiate, finalise, execute, and do all the things necessary to administer the contract on behalf of Council;
D. Delegates to the Chief Executive Officer the power to amend the contract up to 11.5% of the total contract value;
E. Approve the budget allocation for the supporting services and costs associated with the delivery of this program. This includes:
i. $200,000 for cost recoverable project support. This is recovered monthly via the directed Disaster Reconstruction Funding Arrangement finance program.
ii.$486,751 for non-recoverable costs but essential to the receipt of grant funds and delivery of reconstructed assets.
Carried.
For:Cr Karen Finzel, Cr Jessica Phillips, Cr Nicola Wilson
Against:None




This summary follows this item’s minutes. The established voting totals use their existing method while differences are checked against the full records.

What was said?

Named discussion on NoosaWatch TV

These actual transcript passages match the item’s wording. The start and end of the item’s discussion are not yet confirmed; these excerpts are not measured item airtime or exact decision moments.

1 suggested discussion start time
  • 600.0 seconds on the council source timeline · Recording time not yet verified. The end of the discussion is not yet confirmed.

The supporting record

Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.