ECM_16693990_v1_APPROVED Change to Existing Approval 152005 220 01
Attached to the e-mail 132005.220.04 Request a Change Existing Approval.
152005.220.01
103. All physical site control measures must be installed and maintained until all
Operational Works have been completed and accepted on maintenance. The
approved erosion and sediment control plan must be adhered to at all times.
Survey
104. Where existing road boundaries are less than 9m from existing or proposed road
centrelines, or less than 3m from the toe or top of batters of existing or proposed
roads or less than 10m from the top of creek embankments, the lot layout shall be
amended to provide sufficient land in Road Reserves and Park Reserves to achieve
these clearances.
Prior to endorsement of the Plan of Survey, the applicant shall submit to Council a
certification of compliance from a licensed surveyor
105. Prior to endorsement of the Plan of Survey, three (3) State Survey Marks shall be
provided within the road reserve of the development and these shall be spaced to
maximise their use.
The State Survey mark shall be levelled and located to the requirements of Council’s
Works Directorate and a ‘Form 6’ shall be submitted for Council's records.
Each State or other Permanent Survey Mark shall be installed clear of overhead
vegetation, making it suitable for Global Positioning Equipment, and accurately
connected to at least two real property corner by a licensed surveyor.
106. As Constructed drawings and data shall be certified by a qualified experienced civil
engineer for design intent, and a licensed surveyor shall certify the cadastre and the
location, level and type of all services and structures. All of which shall be submitted
to Council for checking and for Council’s records.
The data must fully detail levels for all engineering works including but not limited to
drainage structures, finished ground levels and pavement surface levels. The data
shall be submitted in the Asset Design and As Constructed (ADAC) digital format.
(Guidelines on the use of ADAC are available at www.adac.com.au).
Approval of works ‘on maintenance’ will not be granted until all As Constructed
information has been supplied and accepted by Council.
General Engineering
107. A suitably qualified registered professional engineer shall prepare engineering
drawings and specifications for all engineering works, which shall be submitted in
conjunction with an application for a Development Permit for Operational Works. In
this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is
to be submitted in conjunction with any application for Operational Works.
108. Digital detailed design drawings and calculations shall be submitted with any
application for a Development Permit for Operational Works in respect of roadworks
and stormwater drainage works. To avoid conflict with underground pipes or services,
all existing and proposed services required by the development shall be shown on the
plans.
109. To facilitate production of As Constructed drawings it is suggested that all design
drawings are submitted in the Asset Design and As Constructed (ADAC) digital
format.
110. The person acting on this permit shall apply and obtain for all other necessary permits
including crane permits, road opening permits, hoarding permits, footpath occupation
permits and/or any other approvals required under any other Act.
111. Any damage caused to any public utility during the course of construction shall be
repaired to Council’s standards and at no cost to Council.