ECM_16693990_v1_APPROVED Change to Existing Approval 152005 220 01
Attached to the e-mail 132005.220.04 Request a Change Existing Approval.
152005.220.01
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. The applicant is advised that development contributions and infrastructure charges
applicable to this development approval have been based on the following estimates for
Uses Class/ Uses and applicable quantities:-
Existing Development Approved Development
Approved
Existing Use Existing
Use Class / Approved Quantity
Class / Use Quantity
Use
22 Industrial Lots, Plus 1
Balance Lot Being Lot 50
Water & Sewerage Headworks
Industrial Contributions based on Lot
One Vacant
Vacant Business Type area of 47,108m 2
Allotment
2 Open Space & Pathway
Contributions based on 40%
Site Cover = 18,844m2 Use
Area
2. The applicant is informed that payment via credit card transaction will not be an
acceptable method of payment for development contributions conditioned in this permit
or for infrastructure charge notices issued separately.
3. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991
Act if the cost of operational works exceeds $80,000, then a portable long service leave
levy is required to be paid. In accordance with Section 77.(1) of the Act, Council is
required to sight the approved form issued by the Building and Construction Industry
(Portable Long Service Leave) Authority that confirms that the requirements of the Act
have been satisfied. A statutory declaration outlining the cost of the operational works
must be submitted to Council with the lodgement of any application for operational
works over the site
4. The Environmental Protection Regulation 1998 and Local Law No.12 prohibit a builder
from making noise from:-
Monday to Saturday, before 7:00am or after 6:30pm
Sunday or public holiday, at any time.
A maximum penalty of $1,500 applies to an offence under these provisions
5. In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt,
mud, paint, cement, concrete, builders waste or rubbish shall not be permitted to enter
or be placed where it could reasonably be expected to move into a roadside gutter,
stormwater drain or a water course. On the spot fines apply for such offences.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
carries out an activity must take all reasonable and practicable measures to ensure the
activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
duty of care. Substantial monetary penalties may apply to individuals or corporations
breaching this duty of care. Injunctions may also be issued by the Land and Resources
FM1512s/1-07/04/2010 Page 16 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original