ORDINARY MEETING MINUTES 17 OCTOBER 2024
Designs for Resilience 80% Draft Plan released in June 2024 cost to produce?
Response provided by Acting Director Infrastructure Services, Shaun Walsh
Thank you for the question and interest in the Noosaville Foreshore. The cost of
the first draft Noosaville Foreshore Infrastructure Master Plan, as released in June
2024 was $336,305 total budget. These costs include all consultants costs, staff
costs and all on costs such as community engagement associated with the
project. As this is an infrastructure project for future assets.
It is important to note that the project was also subsidised by a $100,000 grant
provided by Queensland Government QCoast2100 grant to provide coastal
resilience concepts integrated into the foreshore masterplan.
In consideration of these costs, it is important to note that the Noosaville Foreshore
covers over 2 kilometres, is the largest and most popular coastal urban park in
Noosa, and has many users and complexities associated with a design process.
The infrastructure master plan, as well as providing community certainty, also
provides a platform for future investment through grants and other income
sources. Council has projected $10millions of dollars in necessary asset renewal
costs on the Noosaville Foreshore including revetments walls, pathways,
stormwater pipers, carparks, playgrounds, river pontoons and jetties and park
furniture. Rather than rely on rates revenue from residents it can seek grants to
subsidy and supplement necessary infrastructure costs. Funding partners are
seek clarity articulated through an endorsed framework or master plan to ensure
astute investment.
Recent examples of Council Master Plans providing an astute investment platform
include:
Noosa Biosphere Trails Implementation Plan - $30k has resulted in $3.2
million grant funding which 108 times the original investment.
Noosa Cycling and Walking Strategy - $250k has resulted in $11.3 million
grant funding which 45 times the original investment.
Cooroy Sporting Complex Master Plan - $50k has resulted in $6.3 million
grant funding which 126 times the original investment.
Noosa District Sports Complex Master Plan - $50k has resulted in $4
million which 80 times the original investment.
These grant funding examples provide compelling examples of the value of Master
Plan in the maintenance and improvement of valued community assets through
grant funding, rather than relying solely on residents rates and why it is very
important for Council to continue to prepare master plans for critical assets.
(Examples more fully described below but won't be part of the response)
Master Plan Cost to Grants funds obtained Return on
Project Council to Investment
prepare from Grant
Plan Revenue
Noosa $30k $1.61 million Local $30k has
Biosphere Economic Recovery resulted in
Trails Program Queensland $3.2 million
Implementation Reconstruction Agency, which 108
Plan Queensland Government times the
original
investment.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.