Bushfire Management Plan Review Report_June 2018

Attached to the e-mail URGENT - RAL18/0023 - Essential Bushfire Management Review - Noosa Civic.

Attached to the e-mail FW_ URGENT_ Essential Bushfire Management - Noosa Civic.eml, inside FW Bushfire Management - Noosa Civic.msg.

Attached to the e-mail FW URGENT Essential Bushfire Management - Noosa Civic.msg.

of 36

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Report on Review of Bushfire Situation at Noosa                                            Q.I.C.
Civic




No actions are recommended or needed.


Area 4
This area of 13ha is attached to Covenant Areas J & L which total 1.65ha. These three
areas are not separable from a bushfire perspective and need to be considered as a
management unit.


Covenant Area J is a constructed drainage easement and management other than the
edge adjacent to the development is difficult.


The fuel loads in Area 4 are 15 years old (last unplanned fire was in 2003) and up to 15
tonnes/ha. (see Photograph Nos. 9 & 10)


It is not proposed for any development in this area in the foreseeable future and as such
some ongoing management is required to maintain a safe environment for the nearby
Noosa Civic development.



These necessary actions include upgrading access, establishing small management units
suitable for fuel reduction techniques. The necessary actions are detailed in Section 4.1.1
and 4.1.2 of this report.


Confirming a vehicular access from Hofmann Drive around the interface between the
existing development and the adjoining Area 4 vegetation is very important for any
defence capabilities. (see 4.1.4)


The long term establishment of a southern separation access should also be investigated.
(i.e. 4.1.3)


Area 5
This small narrow area of 1.3ha is largely a drainage line. (see Photograph No. 11)




  18-028 Report                                                 Commercial-in-Confidence
                                                                                 Page 9
Log in to download the original file

Bushfire Management Plan Review Report_June 2018.pdf · 6.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.