Please note: 1 April to 30 June 2026 — Minor Disruption: 17 detailed rows versus 16 in the introductory summary. This chart counts the detailed rows.
Please note: 1 April to 30 June 2026 — On Track: 52 detailed rows versus 53 in the introductory summary. This chart counts the detailed rows.
Published progress observations by Reported progress
Published progress observations
Each initiative listed in the selected operational-plan reports is counted once per report. Progress follows Council’s own descriptions; different reporting periods are kept separate. Select a bar to inspect its records.
The Pathway Delivery Plan is being progressed through the Infrastructure Capital Works Program. The 2026-2027 Budget and Long-Term Financial Forecast include resources for the planning of an additional ten pathway projects across the shire,
Additional administrative resourcing has been of great benefit to accelerate artist uptake of the directory. The site continues to grow, and back-end functionality improvements are implemented to improve administrative efficiency.
Arts & Cultural activities continue to reflect the objectives of the Plan with a particular emphasis on supporting professional creatives in the region, promoting public art development and maturing the uses of our arts facilities to suppor
Following determination of the preferred corridor option, TMR is now assessing staging options within the Government Election Commitment budget. Council teams are providing collaborative supporting to achieve project milestones. A Controlle
Revised design Includes adaptable construction and incorporating improved aesthetics and amenity to better align with stakeholder expectations. Revision to timing and cost under negotiation with Qld Reconstruction Authority (QRA) and Nation
The Library of Things was launched in February by the Mayor. Lending items are being enthusiastically used by the community and the collection continues to grow. Processes and administration of the library continue to be refined.
The Cooroy Oval lighting project is complete. The Cooroy Gymnastics extension project continues to progress, as does the completion of the Noosa Netball Clubhouse at NDSC, both being delivered as projects arising from the precinct master pl